The 4-day/5-night (104-hour) full
highway closure and traffic detour in March 2012 allowed the City’s contractor to install a new Hwy 213 bridge using
a rapid bridge construction technique. This construction method:
- shortened
the duration of project construction by approximately 6 months, and
- enabled the contractor to keep every Hwy 213 travel lane open in the daytime during all but 4-days of the
construction process.
In contrast, if the Jughandle
Project were to use a traditional staged bridge construction method, it would have required 12-16 months of continuous—24-hours
a day/7-days a week—closures of at least two travel lanes on Hwy 213!
Rapid Bridge Construction
The City’s
contractor began building the new Hwy 213 bridge next to the highway on a temporary support system, where its construction
had little to no interference with traffic. By late
March, the bridge was ready to move into its permanent position, and the contractor worked around the clock to complete
its construction.
The four‐day/five‐night process began
by removing an approximately 130‐foot long section of roadway on Hwy 213. This included excavating approximately 900 cubic yards of asphalt
and between 6,000 and 8,000 cubic yards of material beneath it.
Next, the crew used rollers, threaded rods, and jacks to pull the bridge
superstructure into position over the new permanent foundations. The contractor
then used hydraulic jacks to uniformly lift and lower the bridge into place. The connection between the bridge and its supports was
secured and the roadway paved, allowing vehicles to cross the new bridge within 48 hours of its installation.
A time lapse viedo of the bridge installation
is available on the construction cam page.
More information
Travel on Hwy 213
Information for Bicyclists